Post-quantum product release dates

When this applies​

You are planning or tracking one asset whose migration depends on a supplier release, your own testing, or a fixed support end.

Do this​

Handbook practice: Record four dates for one asset:

  1. Vendor release — when the supplier says post-quantum capability ships.
  2. Testing — when your interoperability and performance tests finish.
  3. Production deployment — when the construction is live for users.
  4. End of support — when the supplier stops security fixes for the release line you rely on.

Authority recommendation: The UK NCSC timelines, modified 3 August 2026, United Kingdom, include milestone rows that depend on when suppliers deliver updates, including long-lived hardware roots of trust in the 2028 plan row.

Authority recommendation: NIST IR 8547, October 2026, United States, states that where a device cannot update its signature check later, and it will still be in use when a cryptanalytically relevant quantum computer exists, the device should be designed to require quantum-resistant signatures on the executable code.

Keep this evidence​

The priority record or migration plan row with all four dates, the supplier source, and the owner.

Example​

Example: The supplier moves key-establishment release from June 2027 to October 2027. The production deployment date moves to November 2027. The end-of-support date for the current release line stays December 2028. The priority record is updated with the new production date rather than left on the old release date.

Limits and next page​

This page does not negotiate the supplier answer. The next page is Vendor plan.

Sources​

  • UK NCSC, Timelines for migration to post-quantum cryptography, modified 3 August 2026. Timelines
  • NIST, Transition to Post-Quantum Cryptography Standards (NIST IR 8547), October 2026. NIST IR 8547